| Progress of the 'Writers Block', Super Duplex Holiday Accommodation. | |
|
SEPTEMBER 2008. EXCAVATIONS FOR FOUNDATIONS STARTED. ACCESS ROAD INSTALLED. |
|
|
OCTOBER 2008. SHUTTERING FOR FOUNDATIONS FITTED. CONCRETE POURED FOR FOUNDAIONS. |
|
|
NOVEMBER 2008. |
|
|
|
DECEMBER 24th. 2008. FIRST LINTELS INSTALLED. |
|
|
JANUARY 10th. 2009. |
|
|
FEBRUARY
2nd. 2009. |
|
|
FEBRUARY
27th. 2009. |
|
|
|
|
|
MARCH 20th.
2009. BALCONIES INSTALLED. |
|
|
APRIL 17th.
2009. |
|
|
MAY 1sth.
2009. ROOF SLATES STARTED. |
|
|
MAY 10th.
2009. |
|
|
MAY 29th.
2009. LOOKING TOWARDS MAJOR JOHNS LAKE & CLAWTON. |
|
|
JUNE 7th. 2009.
|
|
|
|
|
|
JUNE
12th. 2009. |
![]() |
JULY 4th. 2009. |
|
|
AUGUST
19th. 2009. |
|
|
SEPTEMBER
12th. 2009. |
|
|
OCTOBER 1st. 2009. |
|
OCTOBER 2009. PLASTERING & SOUND INSULATION ONGOING. DIGITAL TV SYSTEMS INSTALLED. |
|
|
NOVEMBER 2009. |
|
|
DECEMBER 2009. STARTED TILING BATHROOMS.
INSTALLING KITCHENS. |
|
|
JANUARY 2010. ELECTRICAL POWER CONNECTED. FOURTEEN INCHES OF LOFT INSULATION FITTED. BATHROOMS & KITCHENS FITTED IN SEVEN UNITS. |
|
FEBRUARY 2010. ELECTRICAL POWER CONNECTED IN ALL UNITS. WATER SYSTEMS COMPLETED IN ALL UNITS. FIVE UNITS COMPLETE AND DECORATED, READY FOR CARPETING. |
|
![]() |
MARCH 2010. DECORATING COMPLETE IN ALL UNITS. PRESSURE TESTING COMPLETE. ALL UNITS CARPETED. CURTAINS & BLINDS FITTED. |
|
APRIL 2010. BALCONIES AND STAIRWAYS FITTED. PATHWAYS AND PATIOS COMPLETE. PAFKING AREAS COMPLETE. EXTERNAL DOORS ON WET ROOMS AND STORAGE ROOMS FITTED. FURNITURE DELIVERED AND ASSEMBLED IN FIRST FLOOR UNITS, |
![]() |
|