Progress of the 'Writers Block', Super Duplex Holiday Accommodation.
 

SEPTEMBER 2008.

POSITION OF THE WRITERS BLOCK MARKED OUT.

EXCAVATIONS FOR FOUNDATIONS STARTED.

ACCESS ROAD INSTALLED.

 

 

OCTOBER 2008. 

EXCAVATIONS FOR FOUNDATIONS COMPLETE

SHUTTERING FOR FOUNDATIONS FITTED.

CONCRETE POURED FOR FOUNDAIONS.

 

 

NOVEMBER 2008. 

GROUND WORK COMPLETE.
GROUND FLOOR BRICKWORK UNDER WAY.

DECEMBER 24th. 2008.

GROUND FLOOR BRICKWORK UNDER WAY.

FIRST LINTELS INSTALLED.

JANUARY 10th. 2009. 

SLOW PROGRESS. GROUND FLOOR BRICKWORK STILL UNDER WAY.

FEBRUARY 2nd. 2009.

GROUND FLOOR ALMOST COMPLETE UP TO FIRST FLOOR.
SCAFFOLD INSTALLED TO FIT REMAINING LINTLES
&
COMPLETE GROUND FLOOR BRICK WORK. 

FEBRUARY 27th. 2009.

COMPLETE UP TO FIRST FLOOR LEVEL.
FIRST FLOOR CONCRETE FLOORS BEING INSTALLED.

MARCH 20th. 2009.

FIRST FLOOR BRICK WORK COMPLETE.
ROOF TRUSSES 50% COMPLETE.

BALCONIES INSTALLED.

APRIL 17th. 2009.

ROOF TRUSSES COMPLETE.
ROOF MEMBRANES BEING INSTALLED.

MAY 1sth. 2009.

ROOF SLATES STARTED.

MAY 10th. 2009.

ROOF SLATES 60% COMPLETE.
TEREYLENE STARTED ON APEXES. 

MAY 29th. 2009.

VIEW FROM WRITERS BLOCK AT THE START OF APPLE BLOSSOM TIME.

LOOKING TOWARDS MAJOR JOHNS LAKE & CLAWTON.

JUNE 7th. 2009.

'ROOF COMPLETED' CELEBRATIONS.


WANDA WAITS IN ANTICIPATION
FOR
KEVIN TO POP THE CORK. 

 JUNE 12th. 2009.

TERYLENE CONTINUING ON SIDES & REAR.
SCAFFOLDING STARTED TO COME DOWN.
GROUND FLOOR PATIO DOORS & WINDOWS FITTED.  

JULY 4th. 2009.

SCAFFOLDING REMOVED.
FIRST FLOOR PATIO DOORS & WINDOWS FITTED.
FIRST FIT PLUMBING & ELECTRIC,S STARTED.  

AUGUST 19th. 2009.

FIRST FIT WOOD STARTED.
CEILINGS AND INSULATION STARTED.
TERELENE ONGOING TO THE BACK OF UNITS.  

SEPTEMBER 12th. 2009.

TEREYLENE FINISHED.
FIRST FIT PLUMBING & WOODWORK FINISHED. 
DRAINS INSTALLED & FINISHED.
CONCRETE AREAS HARD-CORED & READY FOR LAYING. 

OCTOBER 1st. 2009. 

FIRST FIT ELECTRICS FINISHED.
PLASTERING & FITTING SOUND INSULATION STARTED. 

OCTOBER 2009.

PLASTERING & SOUND INSULATION ONGOING.
DIGITAL TV SYSTEMS INSTALLED.
 

NOVEMBER 2009. 

SOUND INSULATION PASSED TESTS.
PLASTERING & SOUND INSULATION COMPLETE IN SIX UNITS.
FLOOR SCREED ON SIX REMAINING UNITS INSTALLED.
SECOND FIT WOODWORK STARTED.
FIRST FOUR BATHROOMS BEING INSTALLED.
FIRST FOUR KITCHENS BEING FITTED.

 

DECEMBER 2009. 

INSTALLING BATHROOMS.

STARTED TILING BATHROOMS.

INSTALLING KITCHENS.
DECORATING STARTED.
WOODWORK BEING COMPLETED, INTERNAL DOORS BEING FITTED.

  JANUARY 2010.

ELECTRICAL POWER CONNECTED.
FOURTEEN INCHES OF LOFT INSULATION FITTED.
BATHROOMS & KITCHENS FITTED IN SEVEN UNITS.
  FEBRUARY 2010.

ELECTRICAL POWER CONNECTED IN ALL UNITS.
WATER SYSTEMS COMPLETED IN ALL UNITS.
FIVE UNITS COMPLETE AND DECORATED, READY FOR CARPETING.
MARCH 2010.

DECORATING COMPLETE IN ALL UNITS.
PRESSURE TESTING COMPLETE.
ALL UNITS CARPETED.
CURTAINS & BLINDS FITTED.
  APRIL 2010.

BALCONIES AND STAIRWAYS FITTED.
PATHWAYS AND PATIOS COMPLETE.
PAFKING AREAS COMPLETE.
EXTERNAL DOORS ON WET ROOMS AND STORAGE ROOMS FITTED.
FURNITURE DELIVERED AND ASSEMBLED IN FIRST FLOOR UNITS,